Moshava TiberiasA new community on the Poria ridge.
EN

HEENFR

Drone photo Drone photo, 18.11.2025 · © White Label Real Estate

Home The plan Timeline & construction updates

The plan

Timeline & construction updates⁠

01

So far

  1. 2014 · The Tiberias master plan is approved, with 13 development areas. The Moshava is one of them. Reported

  2. 20 June 2016 · The district committee discusses putting the Moshava A plan on deposit. Official record

  3. 15 November 2017 · Approval of plan 207-0351742 is published: 1,984 homes on about 773 dunam. In the approved plan

  4. 14 May 2018 · The first land tender, 334/2017, closes without a single bid for its 304 Dira BeHanacha homes. Official record

  5. 24 December 2018 · The first plots sell: 144 homes, to Yuvalim Mechir LaMishtaken and Alum-Net. Official record

  6. 9 December 2019 · A tender for 660 homes draws no bids. In June 2020 the same happens with 72. Official record

  7. 28 December 2020 · Every bid in tender 172/2020 is ruled invalid. Official record

  8. 28 July 2021 · 112 houses sell to Traklin and America Israel. Official record

  9. 4 August 2021 · A week later, tender 323/2020 sells 888 homes to three companies. Official record

  10. 30 January 2022 · Sagi Almakayes wins plots 701 to 704, with 32 units. Official record

  11. 1 August 2022 · The Israel Land Authority names the winners of the target-price tender: 324 homes, 211 of them at target price. Official record

  12. September 2022 · The city signs a framework agreement worth about ₪2.7 billion for 7,400 homes across Tiberias. Reported

  13. 22 September 2022 · Self-build lottery: 115 plots, 181 units. Official record

  14. 20 September 2023 · A decision to put the Moshava B plan on deposit. Official record

  15. End of 2023 · National statistics still count no housing units in the neighbourhood. Reported

  16. 7 October 2024 · The Moshava B deposit is published in the official gazette. Official record

  17. 30 April 2025 · Tender 108/2025, for self-build plots, is published. Official record

  18. 28 July 2025 · The Transport Ministry and Netivei Israel announce that about 6 km of Route 768 will become a dual carriageway, with ₪45 million approved to finish the works. Official record

  19. 11 August 2025 · The national infrastructure committee decides to advance the Galilee Railway plan, TTL 195, and picks a route. This is the planning stage. Official record

  20. 26 October 2025 · Approval of Moshava B is published in the gazette: 3,919 homes on about 739 dunam. In the approved plan

02

Coming up

  1. Next step

    4 November 2026 · Registration opens for tender 108/2025: ten self-build plots, 15 units. Some were already offered in tender 364/2021. Official record

  2. 14 December 2026 · Registration closes. Official record

03

What it depends on

  • The Moshava A plan sets its own conditions for building and for moving in. A building permit waits for a registered subdivision of the land, approved plans for roads, water, drainage and power, and a building plan for the whole area. In the approved plan

  • No home can be occupied before it is connected to the public sewer. In the approved plan

  • Construction goes in two stages, the western compound first and then the eastern one. Each stage brings housing, public buildings and infrastructure together, and the local committee may change the order. In the approved plan

  • Route 768 runs along the southern edge of the neighbourhood. In the approved plan Detailed design for widening it is complete; no finish date has been published. Official record

Read more (1)
  • Moshava B mixes private land with state land. Reported Its plan redraws the plots even without the owners' consent. Official record

The Moshava B area with its first roads, the Kinneret behind, November 2025